Intro image for About page Intro image for About page

About Inch Cape

At 1.1 gigawatt Inch Cape is one of Scotland’s largest offshore wind farms. Sited in the North Sea, 15 kilometres off the Angus coast, its onshore transmission infrastructure is in East Lothian where the project connects to the national grid. Inch Cape is now in construction with full operation due in 2027.

Inch Cape’s offshore site covers a total of 150 square kilometres, roughly the size of the island of Hoy in Orkney. It will comprise 72 wind turbine generators, each up to 274 metres tall, installed on a combination of monopile and jacket foundations in water depths ranging from 34 metres to 64 metres.

The monopiles used are amongst the world’s largest with lengths of up to 105 metres, a maximum diameter of 11.5 metres and with the heaviest weighing 2700 tonnes. The jacket foundations are up to 89 metres tall with the heaviest weighing 2250 tonnes.

A total of 150 kilometres of array cables will bring the power to a single 66 kilovolt (kV)/220kV offshore substation platform on a 68-metre jacket foundation at the heart of the wind farm. Electricity from the offshore substation will be transmitted 85 kilometres via two 220kV subsea export cables to landfall in Cockenzie, East Lothian. 

The export cables will join a short section of onshore export cable which will connect into the new 220/275kV onshore substation constructed on the brownfield site of the former coal-fired Cockenzie Power Station. The substation will comprise two super grid transformers, shunt reactors, harmonic filters, static var compensators and additional electrical equipment. 

From the substation, the power will be transported around 300 metres underground to the existing Scottish Power Energy Networks (SPEN) 275/400kV substation. From here it will enter the national transmission system on its way to providing green electricity to UK homes, businesses and industry.

The project will be operated and maintained out of a purpose-built facility at the Port of Montrose, in Angus.

Inch Cape represents a significant investment in the UK’s energy infrastructure with associated economic opportunities and community benefits. Potential suppliers can register their interest in working with the project and its key contractors via our supplier database.

More than £3.5 billion

investment in the UK’s electrical infrastructure

Significant contribution

to the UK target for 50GW of offshore wind capacity to be installed by 2030

10%

of the Scottish Government’s 11GW offshore wind ambition for 2030

394 UK companies

have contributed to the project to date (mid 2026)

179 Scottish companies

have contributed to the project to date (mid 2026)

£4.7 billion

to be spent in the UK over the lifetime of the project

Use of brownfield site

in East Lothian including existing grid capacity and established transmission infrastructure

More than 55%

UK content to be delivered over the life cycle of the project

New facility

constructed at the Port of Montrose for the project’s operations & maintenance phase

More than 50

long-term skilled jobs will be created locally

Half the homes in Scotland

could be powered by the green energy generated

2.5 million

Reduction in tonnes per annum  in carbon emissions once operational, compared to using fossil-fuels*

* Using DESNZ’s “all non-renewable fuels” emissions statistic of 437 tonnes of carbon dioxide per GWh of electricity supplied in the Digest of UK Energy Statistics (July 2024) Table 5.14 (“Estimated carbon dioxide emissions from electricity supplied”). Carbon reduction is calculated by multiplying the total amount of electricity generated per year by the number of tonnes of carbon which fossil fuels would have produced to generate the same amount of electricity.

2008
Inch Cape as a concept first came about in 2008 after the site was selected for further investigation by The Crown Estate (now managed by Crown Estate Scotland). 
2009
An initial bidding round resulted in exclusivity rights being awarded in 2009. Following a Scottish Territorial Waters Strategic Environmental Assessment, Scottish Ministers decided to progress the Inch Cape site, along with four others. 
2011
In 2011 an agreement for lease was awarded. The wind farm ownership, design and installed capacity has changed and evolved since that time and the project has been able to take advantage of new technologies and innovations as the wider offshore wind industry also developed.
2014
Since receiving its original consent in 2014, Inch Cape has reduced the number of turbines and increased the proposed installed capacity while retaining its original offshore site.
2019
In spring 2019, it received approval for a revised wind farm design, opening the door to new turbine technology and a reduction in turbine numbers from 110 to 72. This meant the project could reduce construction time, costs and potential environmental impacts.
2020
In summer 2020, Inch Cape secured approval to increase its generation capacity to one gigawatt (from 700MW) so the project could utilise the latest technology and maximise its efficiency within existing consent parameters.
2022
 The consented project was awarded a contract for difference in the UK Government’s 2022 Allocation Round 4.
2023
Aerial of construction site
 In October 2023, its onshore enabling works were completed in readiness for the main civil engineering works which started in early 2024.
2024
 Inch Cape was awarded a second contract for difference from Allocation Round 6 topping-up the 2022 award.
2024
Transformers on offshore substation
Work progresses on the Cockenzie onshore substation and with the offshore substation and jacket foundation at Wallsend.
2025
Inch Cape reaches financial close and kicks off offshore construction.
2025
Both the marine coordination centre and offshore construction base established at Montrose Port
2025
Cable deck lift tops off jacket foundation fabrication at Smulders’ Wallsend yard and creates a new temporary landmark on the Newcastle skyline.
2025
Offshore Construction Supplier event for local businesses was held at Montrose Town Hall with more than 150 delegates hearing about contract opportunities with Inch Cape.
2025
Offshore substation and jacket foundation loaded out on to Heerema Marine Contractors’ barge and sail away
2025
Installation of Siemens Energy Offshore Transformer Module and 68m jacket foundation at the Inch Cape site (21 kilometres from shore)
2025
Construction starts on Inch Cape’s new operations & maintenance facility at the Port of Montrose.
2025
First export cable installation completed by CMOS Installer. Three 28-kilometre sections are installed with the cable pulled in at both the offshore substation platform (pictured) and the Cockenzie substation site.
2025
The first shipment of XXL monopiles arrive in the Port of Leith marking a new phase in the wind farm’s offshore construction. The first monopile is installed in December 2025.
2025
Les Alizes vessel departs Leith
The first monopile foundation is installed offshore marking the start of a key offshore construction phase for the project
2026
Fifteen transition pieces arrive in Leith for offloading, the first of a total of 54 which will be marshalled at the port.
2026
First three jacket foundations arrive in the Port of Leith for offloading, creating a new temporary skyline.
2026
DA College and ICOL sign MOU in Montrose
Inch Cape and Dundee & Angus College sign a memorandum of understanding setting out how they will work together to develop skills for the growing offshore wind sector and support the development of the Port of Montrose Energy Skills Hub.
2026
The first section the second export cable departs Blyth for installation offshore. A total of three 28 kilometre sections will be laid and jointed.
2026
Completion of the installation of all 54 of the project’s XXL monopile foundations at the offshore site.
2026
Completion of the installation of all 54 transition pieces by heavy lift vessel Seaway Alfa Lift. The transition pieces sit on top of the monopiles and once installed are bolted and grouted into place.

Inch Cape Offshore Wind Farm is owned by Inch Cape Offshore Limited, an equal joint venture between Edinburgh-based renewable and sustainable energy company, Red Rock Renewables and Ireland’s leading energy company, ESB.  

Red Rock Renewables is an Edinburgh-based investor, owner and operator of renewable energy projects. Its team of around 80 members is passionate about delivering clean, affordable energy and supporting the UK’s and wider Europe’s net zero ambitions. 

ESB operates across the electricity market on the island of Ireland: from generation, through transmission and distribution to the supply of customers with an expanding presence across Great Britain. In 2017, ESB opened its office in Glasgow to spearhead further development of renewables, in particular onshore and offshore wind, across Scotland.

Next steps

By mid-2027, all 72 wind turbines will be installed and commissioned, and operations and maintenance started.

Our galleries

View videos and photographs of the Inch Cape project including our onshore and offshore construction work and our involvement with the community, local schools and colleges.

Document library

Our document library contains a range of written materials including project publications and newsletters, consent documents and health, safety and environment information.